Following its production, commissioning of the rake was delayed for a few months after ICF flagged several manufacturing defects, which BEML later addressed.

The 16-coach rake comprises 11 three-tier AC coaches, four two-tier AC coaches and one first-class AC coach, with a total seating capacity of 823 passengers.Photo | Express B Anbuselvan Updated on: 22 Jun 2025, 7:42 am 2 min read Follow Us CHENNAI: It has been over six months since the prototype of the Vande Bharat sleeper version was dispatched from the Integral Coach Factory (ICF) for trials and testing, but it is yet to receive clearance for operation. The 16-coach prototype, designed by ICF and manufactured by the Bengaluru-based public sector company BEML (formerly Bharat Earth Movers Limited), was built at a cost of Rs 120 crore.

Following its production, commissioning of the rake was delayed for a few months after ICF flagged several manufacturing defects, which BEML later addressed. Although the Research Designs and Standards Organisation (RDSO) successfully completed speed trials at 160 kmph in January, the train is still awaiting approval from the Commissioner of Railway Safety (CRS), officials said.

Sources indicate that the CRS has raised certain objections regarding the design and expressed reservations about some of the safety features incorporated in the train. However, the Railways has asserted that there are no issues with the electrical or mechanical components.

 VB’s sleeper version is equipped with Kavach

ICF General Manager U Subba Rao told TNIE that the CRS had raised a few queries concerning the prototype, which have already been addressed. “A detailed response has been sent. The clarifications pertained to minor technical aspects. There were no major flaws in the prototype,” he said.

After receiving the prototype from BEML, ICF identified more than 73 design and technical issues, particularly related to safety. These included concerns about crash buffers, fire barrier walls, and the hooks connecting the middle and upper berths. These issues led to the project missing its initial deadline by a few months.

Rao stated that all concerns raised by ICF had been resolved. “It’s just a matter of time before the 16-coach sleeper version is cleared for operation by the Railway Board. We have already received orders to build nine more Vande Bharat sleeper trains this financial year,” he added.

ICF has incorporated several enhanced safety features in the sleeper version. The rake is also fitted with the Kavach Train Collision Avoidance System, crashworthy couplers, front and side crash buffers and a fire detection system.

In January, the train successfully completed oscillation trials, emergency braking tests and evaluations of its control and electrical systems conducted by RDSO in Lucknow. It also underwent high-speed testing at 180 kmph in the Kota division, along with short- and long-distance trial runs, before being submitted for CRS approval.

The 16-coach rake comprises 11 three-tier AC coaches, four two-tier AC coaches and one first-class AC coach, with a total seating capacity of 823 passengers.

No comments:

Post a Comment

SC orders all-India audit of pvt & deemed universities Focus On Structural Opacity & Examining Role Of Regulatory Bodies

SC orders all-India audit of pvt & deemed universities Focus On Structural Opacity & Examining Role Of Regulatory Bodies   Manash.Go...