Railways ignores speed restriction on 252 old bridges in bad shape
NEW DELHI: In a major safety lapse, Railway has found that out of 275 railway bridges across the country that need rebuilding for they are very old, speed restrictions for trains to pass through has been put only on 23 bridges. What poses a big threat to safe train operations is that trains continue to pass with usual speed on other 252 bridges that are in bad shape.
The Railway Board had sought details of bridges and it was observed that large number of bridges needing rehabilitation existed on some zonal railways since long. The Central Railways has 61 bridges, East Central Railways 63, South Central Railways 41 and Western Railways 42 bridges pending rebuilding.
“It is also observed that in most of the cases, no speed restriction has been imposed and special inspection schedule has also not been prescribed by chief bridge engineers. On the other hand, there are many bridges where speed restrictions have been imposed on condition basis but they are not categorized under ORN-1 or 2 categories,” said the order issued by A K Singhal, Executive Director Civil Engineering.
The railway bridges are divided in three categories – overall rating number 1, 2, 3. Bridges with overall rating number (ORN-1) rating require immediate rebuilding/rehabilitation, ORN-2 ratings are required to be rebuilt on the programmed basis while ORN-3 bridges require special repairs.
Railway Board has now pulled up zonal railways for failing to do a time bound planning for completing the rehabilitation work.
“It seems that proper time bound planning has not been done by railways for rehabilitation of these bridges which creates a doubt whether correct condition rating appropriate to the actual condition of the bridge has been assigned or not. It is also felt that there has been lack of due diligence at Division/headquarter level while revising/confirming the rating,” said Singhal in the order issued last month.
Railway Board has said that the chief bridge engineers (CBEs) should specifically review the position in respect of all bridges assigned in their respective railways and firm up the action plan for their rehabilitation on priority.
A CAG report in 2015 had found that delays in sanctioning of bridgeworks and completion of sanctioned bridgeworks resulted in operation of train services with speed restriction.
It further said that instances of continued operation of speed restriction were noticed on 87 bridges of 13 zones ranging between four to 591 months. Audit assessed an extra expenditure of Rs 103.40 crore on account of operational cost due to continuation of speed restrictions.
“The above demonstrates the casual approach on part of Railways in sanctioning/executing and monitoring of bridgeworks. This resulted in delay in execution of bridgeworks that were identified for rehabilitation leaving the possibility of compromising passenger safety during operation of train services on these bridges. Railways need to ensure an effective monitoring system to be in place for timely execution and completion of bridgeworks,” the CAG report has added.